Latest updates

April 2025

Sophie Andrews, •7 May 2025

Stage 2 seismic resilience upgrades for the main wharf continue. Pt Howard wharf demolition is now complete.

February 2025

Sophie Andrews, •20 Feb 2025

Point Howard Wharf Demolition (HCC project) is 90% complete, Seaview Main Wharf seismic strengthening is ongoing and Brian Perry Civil (BPC) have been appointed as the head contractor to install…

December 2024

Kiri Shannon, •23 Dec 2024

The installation of the new Quick Release Hooks on the new mooring dolphin structures rounds out the works for the year.

October 2024

•31 Oct 2024

The project continues to progress well, with piling works installed for Stage 2 and a preferred route for Stage 3b selected.

August 2024

•27 Aug 2024

Progress on the design and consenting of the Stage 2 section of the pipeline is progressing well.

June 2024

•10 Jun 2024

Stage 3a works have been completed and the Caltex truck stop re-opened to customers.

April 2024

•29 Apr 2024

CentrePort hosted members of the Eastbourne Community for a tour of the wharf and ongoing works at Seaview.  

February 2024

•8 Feb 2024

Construction begins on initial stages for Stage 3.

June 2023

•1 Jun 2023

Meticulous planning has ensured the safe installation of a 70-ton soffit at Seaview Wharf in Wellington, which is believed to be the largest lift from a jack-up barge in New…

March 2023

•1 Mar 2023

Early Monday morning, members of Taranaki Whānui led a dawn karakia and naming ceremony at Seaview Wharf, for Brian Perry Civil's (BPC's) new barge.  
1 2