Latest updates

February 2023

•10 Feb 2023

Last week, Brian Perry Civil’s (BPC’s) new Combifloat barge was constructed and towed to Seaview.

December 2022

•10 Dec 2022

Work is progressing well at Seaview Wharf, with the five piles at the rear of the amenities building on track to be completed in time for the Christmas break.

October 2022

•10 Oct 2022

Good progress continues to be made on the Seaview Wharf upgrade, with piling installation well underway.

August 2022

•16 Aug 2022

June 2022

•8 Jun 2022

April 2022

Will Rossiter, •7 Apr 2022

February 2022

•1 Feb 2022

The Seaview Energy Resilience Project will take place in three stages. Community engagement will take place throughout each stage and we welcome community feedback.
1 2