February 2025

February 20, 2025

Stage 2

·       Point Howard Wharf Demolition (HCC project) is 90% complete, awaiting fuel pipeline realignment to demolish the remaining landward section of wharf.

·       Seaview Main Wharf seismic strengthening is ongoing, with upgrades to elements of the approach wharf to commence in March.

Stage 3b

Brian Perry Civil (BPC) have been appointed as the head contractor to install the new pipeline between the Seaview Rd valve station and the Hutt City fuel storage terminal. BPC are preparing the various management plans required by the resource consents for council approval, and once these are in place it is expected that they will commence site establishment sometime in March 2025.

All the principal supplied pipe, fittings, flanges, valves, induction bends, and other components are expected to be delivered during February. There is a lot of pipe that needs to be stacked!