August 2024
August 27, 2024
Progress on the design and consenting of the Stage 2 section of the pipeline is progressing well.
Z is undertaking an Early Contractor Involvement (ECI) process to bring a contractor on board to finalise the construction methodology, which will enable the detailed design and consent applications to be finished.
We have started engagement with mana whenua and have undertaken both an ecological assessment and a kororā (little blue penguin) survey to help inform the consent application.
Works remain on track for commencement in early 2026 after the wharf upgrade work has been completed by CentrePort and Brian Perry Civil.